In general, grid reinforcement projects create additional hosting capacity for new connections. Depending on the project, its impact can be country-wide or localized to a specific zone within the Belgian high-voltage grid.
This publication considers future grid reinforcement projects according to their timing as outlined in the Reference Grid.
Although the impact of such projects is usually visible in this publication as an increase in hosting capacity over time, the positive impact may be less visible for some specific projects. This is possible because the future evolution of grid users’ reserved and allocated capacity is also considered while computing hosting capacities. In some regions, these reserved and allocated capacities already fill up the extra capacity that would be liberated by the grid reinforcements.